Road over bridges in Tiruchi city expected to be completed by mid-2026, says Durai Vaiko

7 months ago 3
ARTICLE AD BOX
Durai Vaiko, MP, inspects the advancement  of operation  of roadworthy  implicit    span  adjacent   the Railway Junction successful  Tiruchi.

Durai Vaiko, MP, inspects the advancement of operation of roadworthy implicit span adjacent the Railway Junction successful Tiruchi.

Tiruchi MP Durai Vaiko connected Thursday urged contractors and railway officials to expedite the operation of the roadworthy implicit bridges (ROBs) crossed the railway level crossings adjacent the Tiruchi Railway Junction and the Fort Railway Station successful the city.

“Officials person assured maine that the ROB adjacent the Fort Railway Station volition beryllium completed by May 2026 and 2nd signifier of the ROB adjacent Railway Junction by June 2026,” Durai Vaiko told The Hindu said aft inspecting the advancement of operation connected the 2 projects.

Mr. Durai Vaiko said helium had a elaborate treatment with the contractors and officials connected the reasons for the hold successful advancement of the works. “I was told that the rocky terrain that was encountered had resulted successful alternate plans to beryllium worked out. This progressive getting clearances too, starring to the hold successful the operation of the ROB adjacent Fort Station Road. I was besides told that determination was immoderate hold successful getting required worldly for the Junction ROB. I person requested the officials to supply maine regular updates connected the advancement of works.”

Official had assured that the railway information of the ROB adjacent Fort Station would beryllium completed by February aft which the Tiruchi Corporation would instrumentality up operation of the attack roads. The enactment is expected to beryllium afloat completed by May 2026, helium said.

The Railway information of works connected the 2nd signifier of the Junction ROB would beryllium completed by January and the State Highways Department would subsequently physique the attack roads. The enactment is expected to beryllium completed by June 2026, helium added.

The caller span adjacent the Fort Station is being jointly constructed by the Southern Railway Construction Organisation and Tiruchi Corporation. The Southern Railway Construction Organisation volition physique the caller operation successful the railway information astatine a outgo of ₹12 crore.

The Tiruchi Corporation is to laic the attack roadworthy connected either broadside of the caller span astatine a outgo of astir ₹34 crore. The British-built constrictive span was demolished to marque mode for the caller ROB.

Under the 2nd stage, the existing constrictive span crossed the railway enactment adjacent the Tiruchi Junction had been dismantled and a caller 1 was being built by the Railways and the Highways Department. The span would tally betwixt Aristo roundabout and P&T Colony adjacent Mannarpuram.

Published - October 02, 2025 06:13 p.m. IST