Railway projects worth ₹18,489 crore await clearance

5 months ago 1
ARTICLE AD BOX

The South Central Railway’s 10 railway projects are awaiting clearance from the Railway Board (RB), pursuing the completion of tract surveys and submission of elaborate task reports. These projects span a full region of 818.58 km and are estimated to outgo around ₹18,489.71 crore, according to authoritative sources.

The projected caller lines include: Dornakal–Miryalguda (97.45 km) – ₹2,184.45 crore; Ramagundam–Manuguru (207.8 km) – ₹4,014.38 crore; Karimnagar–Hasanparthi (61.80 km) – ₹1,418.60 crore; Bhadrachalam–Kovvur (48.6 km) – ₹1,172.19 crore; Patancheru–Adilabad (136.5 km) – ₹4,398 crore; and Bodhan–Latur (18.40 km) – ₹483.22 crore.

Other pending works awaiting support include: Doubling of Vikarabad–Parli (79.02 km) – ₹1,651.55 crore; Doubling of Mudkhed–Pimpalkutti (47.50 km) – ₹720.19 crore; Tripling and quadrupling of Kazipet–Secunderabad (110.406 km) – ₹22,236.18 crore and Wadi–Guntakal (11.11 km) – ₹210.95 crore.

In addition, 13 ongoing projects covering 1,316.62 km are presently underway, with an estimated outgo of ₹19,688.42 crore. These are expected to beryllium completed implicit the adjacent 5 years.

Projects nearing completion include: Third line between Kazipet and Vijayawada (183.64 km) – by March 2026, and doubling of Guntur–Bibinagar (139 km) – by December 2026. Next successful enactment for commissioning: Rail-over-rail at Pagidipalli (8.54 km) – by March 2027; Bypass lines at Vishnupuram, Nizamabad, Vikarabad, Peddapalli, and Nashkal–Hasanparthi (35.97 km) – by March 2027.

Next successful the pipeline are: Manoharabad–Kothapalli caller line (151.36 km) – by January 2028; Rail-over-rail at Dornakal (10.50 km) – by February 2028; Errupalem–Amaravati–Nambur caller line and Motumari–Vishnupuram doubling – by February 2028

Further up are: Doubling of Mudkhed–Medchal and Mahbubnagar–Dhone (294.82 km) – by December 2028; Third and 4th lines on Secunderabad–Wadi conception (173.18 km) – by December 2030.

Additionally, survey enactment is successful progress for 18 caller projects covering 2,571.25 km, with an estimated outgo of ₹45,620.30 crore. These include: Quadrupling of Kazipet–Balharshah and Kazipet–Vijayawada; Third line between Dornakal–Manuguru, and doubling between Peddapalli–Nizamabad.

Proposed caller lines surveys are between: Vikarabad–Krishna; Patancheru–Adilabad; Dornakal–Gadwal; Adilabad–Gadchandur; Kacheguda (Umdanagar)–Chityal–Jaggayyapeta; Kondapalli–Sattupalli; Kothagudem–Kirandul; Tandur cement cluster–Zaheerabad; Bhupalapally–Kazipet (Hasanparthi) and Bodhan–Bidar.

Surveys are besides underway for high-speed corridors between Hyderabad–Bengaluru and Hyderabad–Chennai, arsenic good arsenic a Regional Ring Rail. These are expected to beryllium completed wrong the adjacent 1 to 2 years. Including the high-speed corridors, the total estimated cost of each projected and ongoing projects stands astatine pproximately ₹1.30 lakh crore, added authoritative sources.

Published - November 26, 2025 08:34 p.m. IST