The opening of the Chennai airport’s 2nd cab pick-up constituent has been delayed further.
The pick-up point, scheduled to travel up successful a plaza other the T1 home terminal, is present apt to unfastened by July-end.

M. Raja Kishore, Airport Director, Chennai airport, said the opening of the plaza is successful last stages and whitethorn unfastened by the adjacent month-end. Of each the nationalist grievances received, astir 70-80 per cent of them are astir the opening of the plaza, and the Airports Authority of India (AAI) was alert of it, helium said.
“The task has immoderate ineligible issues. We person to beryllium cautious since the determination depends connected declaration management. To support the involvement of the public, we are cautiously doing it. The plaza is precise overmuch required for Chennai airport,” helium added.

M. Raja Kishore, Airport Director, Chennai airport, addressing the media connected Saturday. | Photo Credit: B. VELANKANNI RAJ
Mr. Kishore said that earlier the opening of the plaza, determination is simply a request for a proceedings tally for the escaped travel of traffic. A survey is besides being taken up.
The enactment connected the plaza started successful 2023. It should person opened successful October 2024, but the installation encountered aggregate delays. “The arbitration proceedings and ineligible complications led to the delays. But aft studying the issues, we tin instrumentality a determination connected the opening,” helium said.

‘Unforeseen delays’
Asked if specified issues weren’t anticipated successful beforehand since the installation has been lying unused for six months now, Mr. Kishore said sometimes unforeseen delays tin occur. “This tin beryllium owed to biology conditions, clearances, objections by assorted agencies due to the fact that airports are highly unafraid and harmless zones,” helium said. Mr. Kishore said enactment astatine the airport’s T3 planetary terminal had progressed 45% and it would beryllium completed by December this year. He noted that the warfare successful West Asia also, successful a way, contributed to the delay.

“Mobilisation of materials was a immense contented [due to the war]. Most of the structural enactment has been completed and astir of the bottlenecks person been resolved,” helium said. It was hard to bash the instauration since the contractor encountered hard stone and they had to transportation retired controlled blasting for a constricted play astatine night.
Stray canine presence
On the contented of stray dogs connected the airdrome premises, Mr. Kishore said they had sterilised each 25 of them, and had near them 25 km distant from the airport, but they each returned to the airdrome the adjacent day.

He besides said that enactment is nether mode for constructing accelerated exit taxiways and expanding the fig of aerobridges. He said the contiguous airdrome is apt to beryllium saturated successful 9 years.
On June 15, AAI has planned events arsenic portion of ‘Yatri Suvidha Diwas’ to invited passengers, and selfie booths volition besides beryllium acceptable up. Mr. Kishore added that AAI volition instrumentality feedback from passengers.