After the h2o level recedes to 1,613 ft successful the Tungabhadra reservoir by December-end, the installation of caller crest gates would beryllium taken up and would beryllium completed by June 2026, Deputy Chief Minister D.K. Shivakumar informed the Karnataka Legislative Council connected Thursday.
Replying to a question by Basanagouda Badarli, helium said that plan and drawings of the crest gates had been verified by the Chief Engineer of Central Design Organisation, Vijayawada, and certified by Director, Gates Design (NW&S) of Directorate of CWC, New Delhi.
Subsequently the installation enactment of gross no. 19 worth ₹1.66 cr and enactment worthy of ₹ 34.48 crore pertaining to changing of 32 gates had been entrusted to M/s Hardware Tolls and Machinery Project Ltd. Ahmedabad, Mr. Shivakumar said.
“At contiguous retired of gross no. 19 and remaining 32 crest gates, the fabrication of 14 crest gates has been completed, the dismantling process has begun from December 12. It has been planned to statesman installation of the crest gates aft the h2o level successful the reservoir recedes to 1,613 ft by December-end and implicit the enactment by June 2026,” helium said.
The Deputy Chief Minister said that portion Karnataka had released ₹10 crore for the work, Andhra Pradesh had released ₹20 crore and steps would beryllium taken to merchandise the remaining magnitude for the work.