Minister orders fast-track completion of substations to strengthen power supply

5 hours ago 1
ARTICLE AD BOX
Energy Minister Gottipati Ravi Kumar chairing a reappraisal  gathering  astatine  the Secretariat connected  Wednesday.

Energy Minister Gottipati Ravi Kumar chairing a reappraisal gathering astatine the Secretariat connected Wednesday.

Energy Minister Gottipati Ravi Kumar has directed the officials to expedite completion of the powerfulness substations nether operation crossed the State, emphasising that they are important to benignant retired powerfulness interruptions and low-voltage issues.

He besides wants that powerfulness proviso beryllium restored done alternate arrangements whenever disruptions occur, and stresses the request for strengthening the reliability of the energy network.

Addressing a reappraisal gathering connected Wednesday, Mr. Ravi Kumar announced that the authorities planned to present an underground cabling strategy to guarantee uninterrupted powerfulness proviso to captious and exigency work sectors.

He told the officials to instrumentality peculiar measures to guarantee continuous powerfulness proviso to the authorities hospitals truthful that patients did not look inconvenience during outages, and to analyse the show of the generators successful the astir 30 large hospitals crossed the State truthful that switch-over issues owed to powerfulness failures could beryllium avoided.

APCPDCL CMD P. Pulla Reddy, AP-Transco Joint Managing Director G. Surya Sai Praveenchand, Directors, and elder officials of the Energy Department took part.

Data centre needs

In a abstracted review, Special Chief Secretary K. Vijayanand said the authorities prepared a future-ready powerfulness transmission roadmap to enactment the rapidly expanding information centre ecosystem successful and astir Visakhapatnam, which emerged arsenic a preferred destination for planetary exertion companies and infrastructure developers keen connected establishing hyperscale information centres, Artificial Intelligence (AI) infrastructure, unreality computing facilities, and next-generation integer services.

The program includes improvement of a 765kV, 400kV, and 220kV transmission web connecting cardinal substations astatine Pendurthi, Maradam, Palasa,  Achyutapuram, Padmanabham and Makavaripalem, designed to enactment much than 15 GW of information centre load by 2034 with a scope for further expansion.

He stated that the Visakhapatnam portion had already attracted concern proposals from respective salient nationalist and planetary companies, including Google, Reliance, Tata Consultancy Services (HyperVault), CtrlS, and GMR.

As per the AP-Transco’s estimates, 16 large information centre projects were presently nether assorted stages of improvement successful the region, susceptible of generating astir 9.10 GW of IT powerfulness load.

Considering associated infrastructure request and planetary operational standards, the full powerfulness request had been projected to scope astir 15 GW by FY 2036–37. Mr. Vijayanand said a cardinal absorption of the program was the improvement of the Rambilli Data Centre Cluster.

To enactment the large-scale investments projected successful the area, a caller 400/220 kV substation, on with dedicated high-capacity transmission infrastructure and transmission corridors, would beryllium established. Similar infrastructure was besides planned to beryllium developed for emerging information centre hubs astatine Tarluvada, Mudasarlova, Polepalli and Chinnipalem.

Published - June 10, 2026 07:32 p.m. IST