Dredging in limbo at Beypore port amid delay in EIA

2 months ago 1
ARTICLE AD BOX

Dredging astatine the Beypore larboard is yet to resume owed to the hold successful completing the biology interaction appraisal (EIA), raising questions astir the timeline and ecological consequences of the project.

The harbour improvement initiative, launched 3 years agone nether a ₹11.8-crore declaration awarded by the Kerala Maritime Board, was suspended aft dredgers encountered hard laterite stone connected the seabed, complicating the enactment and prompting calls for a reappraisal of biology risks.

According to sources, contractors had expressed doubts implicit the completion of the enactment without a thorough revision of the funds sanctioned. They had besides argued that the laterite stone could not beryllium removed with the accustomed labour unit and machinery.

The authorities had commissioned the National Institute for Interdisciplinary Science and Technology to behaviour an EIA, evaluating imaginable impacts connected sediment movement, sportfishing grounds, and h2o prime arsenic the channel’s extent was projected to summation from 3.5 metres to 8 metres.

A fig of section stakeholders, including exporters and biology activists, had expressed concerns implicit the prolonged procedural delays successful completing the assessment. A section exporters’ forum functionary said dredging would beryllium important for improving navigation and commercialized marine traffic, and that the inordinate hold could impact the aboriginal improvement of the port.

According to the earlier plan, dredging to region virgin worldly from the seabed and deepen the existing waterway was expected to beryllium completed by February 2026. The deficiency of capable draught—the vertical region betwixt the waterline and the bottommost of the ship’s hull—had been restricting vas question to the port. The connection for rider vessel work was besides rejected owed to the long-pending dredging work.

Meanwhile, Port section sources said efforts were connected to resume the enactment aft the EIA. They besides made it wide that due mitigation measures would beryllium considered based connected biology regulations.

Published - March 18, 2026 07:23 p.m. IST