The gait of infrastructure improvement for number acquisition institutions sanctioned nether the Pradhan Mantri Jan Vikas Karyakram (PMJVK) successful Telangana appears slow, with lone astir fractional of the approved buildings completed truthful far.
The PMJVK, earlier known arsenic the Multi Sectoral Development Plan, was launched successful 2008-09 and rechristened successful 2017-19. A associated inaugural of the Centre and the State, the strategy follows a 60:40 cost-sharing pattern. Under the programme, States suggest infrastructure projects successful districts wherever minorities represent implicit 25% of the colonisation wrong a 15-km 'catchment area'.
Official information shows that of the 92 infrastructure units approved nether the strategy — chiefly buildings meant for acquisition institutions — lone 41 person been completed truthful far. Construction is presently nether mode astatine 39 sites, portion 12 projects person been dropped, mostly owed to feasibility-related issues.
Launched arsenic a Centrally-sponsored strategy during the 12th Five Year Plan with a 60:40 cost-sharing ratio betwixt the Centre and the State, the programme approved 92 units crossed Telangana. These see number residential schools, hostels, inferior colleges, Industrial Training Institutes (ITIs) and Common Service Centres (CSCs).
Of the 54 residential schools sanctioned, 19 person been completed. Two of the 5 approved inferior colleges, 12 of the 20 hostels and 1 of the 2 ITIs are complete. Among the 11 CSCs sanctioned, 7 person been completed truthful far.
As for funding, the full approved budgetary outlay for PMJVK projects successful Telangana stands astatine ₹1,170.33 crore, with the Centre contributing ₹712.81 crore and the State ₹457.52 crore. However, budgetary releases from some sides unneurotic magnitude to ₹698.52 crore, leaving ₹471.81 crore yet to beryllium released. Data shows ₹426 crore has been released arsenic the Centre’s stock and ₹270 crore arsenic the State’s share.
At a caller reappraisal gathering chaired by Minister for Minorities Welfare Mohammed Azharuddin, accent was laid connected expediting the completion of pending infrastructure works.
While sources attributed delays to gaps successful money releases, Minorities Welfare Secretary B. Shafiullah said the contented has since been resolved. He said PMJVK buildings person precocious been completed successful Bodhan, Nizamabad and Adilabad. “By this March, different 25 buildings volition beryllium completed. The Chief Minister is peculiar astir Centrally Sponsored Schemes and they volition beryllium completed connected time. Timely reappraisal of the PMJVK projects and their monitoring is being done. In fact, we person projected operation of different 25 buildings for the adjacent year,” helium said.