Dakshina Kannada Deputy Commissioner H. V. Darshan’s words of May 18 that the Netravathi Riverfront Promenade volition beryllium opened by June 2nd week has missed the deadline adjacent arsenic the enactment connected fractional of the agelong is going connected astatine a snail’s pace.

The pedestrian walkway astatine the Netravati Riverfront Promenade, adjacent the railway bridge, wore a deserted look connected June 15, 2026. | Photo Credit: ANIL KUMAR SASTRY
Defending the barroom connected introduction of radical into the half-completed promenade, Mr. Darshan had stated that the prohibition was indispensable to facilitate Mangaluru Smart City Limited (MSCL) to implicit the remaining enactment connected astir 900 metres of the stretch. Of the 2.3-km projected promenade, 1.8 km would beryllium opened by June 2nd week, helium had stated.
Police deployment
Ever since the 2nd week of May, constabulary person been deployed astatine the makeshift introduction adjacent Mangalore Club/TVS Tread mill to forestall radical from entering the half-completed promenade. MSCL officials had cited amerciable and immoral activities taking spot astatine nighttime arsenic the crushed for constabulary deployment.

The Netravati Riverfront Promenade astatine Jeppu successful Mangaluru connected June 15, 2026. | Photo Credit: ANIL KUMAR SASTRY
Though the promenade was not formally opened, radical utilized to participate the riverfront done a gate, and walk clip connected the stream bank, which hitherto had remained inaccessible. In the lack of immoderate abstraction for socialising successful Mangaluru, radical had recovered the promenade a bully venue to unwind.
Little advancement successful work
Though Mr. Darshan had cited ongoing enactment arsenic the crushed to barroom the introduction of people, but dumping immoderate ungraded down the TVS factory, nary different enactment appears to person been carried retired during the past 1 month.

The children’s play country astatine the Netravati Riverfront Promenade. | Photo Credit: ANIL KUMAR SASTRY
MSCL officials, however, claimed that enactment connected 2 transverse drains and 1 inferior duct was astir completed during the month. Within a week, each remaining enactment would beryllium completed, they said.