The Coimbatore Corporation aims year-end completion of 503.67 km of tar roadworthy restoration nether the ₹200 crore peculiar money for 2025–26.
According to Coimbatore Corporation data, of the 3,456 planned roadworthy works, 3,067 covering 443.63 km person been completed. Officials said the remaining stretches are expected to beryllium finished by December 30.
In addition, tenders person been called for laying asphalt overlay connected 1,919 roads covering 25,093 sq. metres astatine an estimated outgo of ₹200 crore, and these works are presently nether way, the officials added.
The Corporation has undertaken 5,215 roadworthy works implicit the past 3 years nether schemes specified arsenic the Tamil Nadu Urban Road Infrastructure Programme (TURIP), the Nagarpura Salai Mempattu Thittam (NSMT), the State Finance Commission (SFC) peculiar fund, and the Corporation’s wide fund. These works, covering a full of 860.69 km astatine an estimated outgo of ₹415.06 crore, person been completed.
24×7 drinking h2o proviso scheme
The 24×7 drinking h2o proviso strategy is being implemented astatine an estimated outgo of ₹646.71 crore successful the 60 wards that existed anterior to the 2011 enlargement of Corporation limits. Of the 33 overhead tanks planned, 30 person been completed and the remaining are nether construction. Of the 75 km of main h2o transmission pipelines proposed, 66.25 km person been laid truthful far, portion 1,747.63 km of the projected 1,798 km of organisation pipelines person been completed. Of the 1.5 lakh planned location work connections, 1,41,062 person been provided. Currently, 95,947 households are receiving continuous 24×7 h2o supply, portion the remaining connections person intermittent supply.
Underground sewerage works
As portion of the underground sewerage works successful Kurichi and Kuniyamuthur, undertaken astatine a outgo of ₹591.14 crore nether the AMRUT scheme, a 30.53 MLD (million litres per day) sewage attraction works (STP) has been completed. Of the 41,318 planned location work connections, 7,435 person been provided, leaving 33,883 pending.
In Vadavalli, Veerakeralam, Kavundampalayam, and Thudiyalur, works costing ₹922.16 crore are 55% complete, including a 34.92 MLD STP. The task plans 67,545 location work connections.
Works successful Vellakinaru, Chinnavedampatti, and Saravanampatti (₹318.20 crore) are 55% complete, with 16,090 location work connections planned.
In the Ondipudur area, works costing ₹179.28 crore person reached 96% completion, with 30,128 location work connections planned.