CMRL likely to open Poonamallee-Porur stretch in January after missing Dec. deadline

5 months ago 1
ARTICLE AD BOX
A operation  of factors including the hold  successful  completion of immoderate   of the presumption    entry/exit points person  led to the hold  successful  operations.

A operation of factors including the hold successful completion of immoderate of the presumption entry/exit points person led to the hold successful operations. | Photo Credit: B. VELANKANNI RAJ

Chennai Metro Rail’s archetypal agelong of the signifier II task from Poonamallee to Porur, a conception of corridor 4, whitethorn miss the December deadline and volition beryllium opened for commuters by January.

According to officials of Chennai Metro Rail Limited (CMRL), they expect to implicit the operation enactment and get the regulatory clearances successful the adjacent fewer weeks and program to commencement bid services successful January on this stretch.

A operation of factors including the hold successful completion of immoderate of the presumption entry/exit points and receiving the indispensable clearances person led to the delay. A fewer mandatory approvals from the Research Designs and Standards Organisation (RDSO) and the Railway Board, Ministry of Railways inactive hasn’t come. “We person escalated the contented to the Ministry of Housing and Urban Affairs. We expect that the [Railway] committee volition supply the signalling support and merchandise the RDSO velocity certificate by December 8 oregon December 9,” an authoritative said.

After this, CMRL has to taxable the exertion to the Commissioner of Railway Safety (CRS) inviting them to inspect this agelong on with the RDSO velocity certificate and an ISI certificate.

CRS volition archetypal analyse each the documents and past would wage a visit. Officials said, if the RDSO velocity certificate is issued adjacent week, past the CRS inspection tin beryllium scheduled successful the 3rd week of the month.

After their inspection, they person to springiness a certificate which volition beryllium the last approval, clearing the decks for opening the bid services to public.

Sources said determination was rather a batch of enactment to implicit successful the operation of the entry/exit points on the Poonamallee-Porur agelong and it is going to beryllium a Herculean task to decorativeness it wrong the adjacent fewer weeks.

“Over 93 per cent of the operation enactment betwixt Poonamallee and Porur has been completed. We person mobilised a immense manpower and volition decidedly implicit the operation earlier the extremity of December,” different authoritative said.

Sources said, it volition beryllium precise hard to implicit the entry/exit structures of 2 stations successful particular, Karayanchavadi and Kumananchavadi. But officials said that of the 2 entry/exit points, 1 volition decidedly beryllium acceptable by December end.

Once the clearances travel through, past CMRL volition person to question a day for inauguration from the Centre and the State government.

Published - December 08, 2025 05:58 americium IST