Except for the conception moving from Arakkonam to Kancheepuram, enactment connected the four-lane access-controlled greenfield task to nexus Bengaluru and Chennai in Tamil Nadu is expected to beryllium completed by June oregon July this year.
In the package from Walajahpet to Arakkonam, a obstruction overbridge is the only structure that has to beryllium completed. “A building belonging to the railways, falling successful the alignment, was removed a fewer days ago. The remaining enactment tin beryllium taken up now,” said a source in the NHAI.
The 105.75-km long information of the expressway successful the State is being constructed successful 4 sections- Gudipala to Walajahpet (24 km, of which 23.85 km has been completed); Walajahpet to Arakkonam (24.5 km, of which 20.35 km is done); Arakkonam to Kancheepuram (25.5 km, of which lone 11 km has been completed); and Kancheepuram to Sriperumbudur (31.7 km, of which 25.25 km is ready).

On the crushed for the hold successful the bundle from Arakkonam to Kancheepuram, a root successful the National Highways Authority of India (NHAI) said that the contractor had been slower than the others successful executing the project, which is wherefore an volition to terminate the contractor had been issued to the company. However, the enactment is yet to commence.
An autarkic source in the know of the advancement of the task said that the contractor had gone to tribunal against the NHAI notice, and that the High Court had disposed the matter directing that the NHAI springiness the institution 1 much opportunity in idiosyncratic to explicate its position. “However, we bash not see this happening successful the adjacent future,” the root said.
A retired NHAI official said the company, that was liable for stalling the full project, should not beryllium fixed much time. “They seem to be dilly-dallying and unnecessarily delaying specified an important task that volition assistance decongest the contiguous Chennai-Bengaluru National Highway. The conception that runs via Karnataka is implicit and the 1 via Andhra Pradesh excessively seems to beryllium successful an precocious stage,” helium said.

Trumpet interchange progressing well Meanwhile, enactment to conception a trumpet interchange (a larger people separator) astatine Sriperumbudur is progressing well. On completion, the six arms of the interchange will allow vehicles travelling from and towards Vellore, Kancheepuram and Chennai to entree the expressway.
According to NHAI sources, enactment to conception the ₹122.03-crore facility, that volition beryllium 1.089 km long, started successful August 2024 and is expected to beryllium over this year. Around 25% of the enactment is done with pre-casting of 198 of the 221 girders completed by the contractor.